Document details Acturis' power outage and response
Software house said it was disappointed by the outage, restored service within two hours and has increased the number of back-up generators.
A document leaked to Insurance Age reveals that Acturis suffered a major power failure in June due to a National Grid lightning strike.
Titled: Acturis System Resilience and Disaster Recovery it stated that a lightning strike impacted power supply to its main production data centre at Global Switch in London at 17:04 on 23 June.
Initially, the emergency back-up generators kicked in as planned but, after several minutes of operation, two of the back-up generators in one of the power stations
Only users who have a paid subscription or are part of a corporate subscription are able to print or copy content.
To access these options, along with all other subscription benefits, please contact info@insuranceage.co.uk.
You are currently unable to print this content. Please contact info@insuranceage.co.uk to find out more.
You are currently unable to copy this content. Please contact info@insuranceage.co.uk to find out more.
Copyright Infopro Digital Limited. All rights reserved.
As outlined in our terms and conditions, https://www.infopro-digital.com/terms-and-conditions/subscriptions/ (point 2.4), printing is limited to a single copy.
If you would like to purchase additional rights please email info@insuranceage.co.uk
Copyright Infopro Digital Limited. All rights reserved.
You may share this content using our article tools. As outlined in our terms and conditions, https://www.infopro-digital.com/terms-and-conditions/subscriptions/ (clause 2.4), an Authorised User may only make one copy of the materials for their own personal use. You must also comply with the restrictions in clause 2.5.
If you would like to purchase additional rights please email info@insuranceage.co.uk